O1050 – S2501 – Raymond Terrace East MYD Consulting Engineers

6% Complete

Project Description

“Accordingly, TUs L700/U900/U2100/L1800/L2600 will be implemented for this site.

* Install one Huawei ASI4517R1/12 port antennas per sector.

* Install five RRUs per sector (L7 RRU(2T4R)*1, U9 RRU(1T2R)*1, L1800 (L18 RRU(4T4R)*1, U21 RRU(4T4R)*1, L26 RRU(4T4R)*1).

* Install two 700/900MHz CS COM2a (E11F13P25) diplexer per sector. * Install two dual band combiners (18/21/23/26) (CS COM3) per sector.

* Install fiber trunk cable per sector for RRU * Max. Tail length between RRU and Antenna is 5m.”

Documents

No documents at this time.

Project Progress

6% Progress

100% Timing

Start Date

January 30, 2018

End Date

February 14, 2018

0/9

Complete Milestones

0/5

Complete Phases

2/25

Complete Tasks

Milestones

0 / 9 Completed

6%

  • 15% Cover sheet + G1 Completion of Cover sheet and G1.
  • 30% G2 + G3 + G4 Completion of G2 and G3.
  • 40% A1 + A2 Completion of A1.
  • 50% F1 Completion of F1.
  • 65% Designer QA QA of FC drawings by designer.
  • 75% Officer QA QA of FC drawings by QA officer.
  • 80% Final Amendment Final amendment of FC drawings.
  • 90% Preparation of HOP Preparation of Hand Over pack.
  • 100% Submit Completed Job :) Submit Hand Over Pack.

Phases

Expand Discussions | 0 / 5 Completed

FC drawings 1 Document 1 / 9 Tasks 0 Responses

12%
Description

Completion of whole FC drawings by designer.

1 of 9 completedTasks

  • Cover Sheet Bahar
  • G1 Bahar
  • G2 Bahar
  • G3 Bahar
  • G4 Bahar
  • A1 Bahar
  • A2 Bahar
  • F1 Bahar
  • Designer QA Bahar

of 1 Approved No Documents Documents

No documents attached to this phase.

Discussion 0 Responses

Leave a Reply

QA Project By QA Officer 1 Document 0 / 1 Tasks 0 Responses

0%
Description

QA FC drawings by QA officer.

0 of 1 completedTasks

  • QA completed Daryoosh Asadi

of 1 Approved No Documents Documents

No documents attached to this phase.

Discussion 0 Responses

Leave a Reply

Final Amendment 1 Document 0 / 1 Tasks 0 Responses

0%
Description

Final amendment on QA officer markups.

0 of 1 completedTasks

  • Final markups amendment Bahar

of 1 Approved No Documents Documents

No documents attached to this phase.

Discussion 0 Responses

Leave a Reply

HOP pack 1 Document 0 / 4 Tasks 0 Responses

0%
Description

Preparation of HOP files.

0 of 4 completedTasks

  • SID Bahar
  • WHS Bahar
  • MYD Certificate Bahar
  • Checklists Bahar

of 1 Approved No Documents Documents

No documents attached to this phase.

Discussion 0 Responses

Leave a Reply

GF site requirements 1 Document 1 / 10 Tasks 0 Responses

18%
Description

All site Requirements for a green field site. (e.g. Geotech. Report, Structure drawings, Structure Certificate, Foundation drawings, Foundation Certificate, Dial Before You Dig, Electrical Design, PVA/ EVA, Power offer and etc.)

If any of above requirements doesn’t apply to this job, then tick the box and in this section discussion write N/A for this specific requirement.

1 of 10 completedTasks

  • Geotech. Report Bahar
  • Dial Before You Dig (1100) Bahar
  • Lease & Licnce Bahar
  • Structural Certificate Bahar
  • Structural Drawings Bahar
  • Foundation Certificate Bahar
  • Foundation Drawings Bahar
  • Electrical Design Bahar
  • Power Offer & EVA/ PVA Bahar
  • Any Other Specific requirement Bahar

of 1 Approved No Documents Documents

No documents attached to this phase.

Discussion 0 Responses

Leave a Reply

Project Discussion 4 Responses to O1050 – S2501 – Raymond Terrace East

  1. January 30, 2018 at 1:03 pm
    Mozhgan

    O1050 – S2501 – Raymond Terrace East
    1.we need the type of fence
    2.we need the type of monopole (concert or steel)
    3.we need plumbing diagram
    4.we need folder of geotechnical
    5.we need lease and licence folder

    • February 9, 2018 at 4:00 am
      Daryoosh

      Please follow it up all on 15th of Feb.

  2. January 30, 2018 at 1:21 pm
    Mozhgan

    i sent an email for Ali about
    (O1050 – S2501 – Raymond Terrace East) (type of fence)

    • February 9, 2018 at 4:00 am
      Daryoosh

      All Raised by me again.
      Please follow it up all on 15th of Feb.

Leave a Reply

Update Status

Document Status Updated

Notifications have been sent.

Loading

Add Document

Upload    Web Address